Zinc Stripping Machine and Auto-Overhead Crane Project in Eastern Europe

In 2022, CHMM won the bid for the 3 sets of Zinc stripping machine and Auto-overhead crane project at a smelter in Eastern Europe. Through this project the owner aims to replace the old zinc stripping machine and improve production efficiency.

The contract includes basic engineering, detailed engineering, supply of equipment, installation supervision, commissioning supervision, and training.

The installation and commissioning of the first set of stripping machines and auto-overhead crane was successfully completed in August 2024, and the production of the second and third sets of stripping machines and operator-cranes is currently underway.

Now the installed stripping machine and auto-overhead crane are running well, which has significantly improved the production efficiency of the owner.